Civil Blogs

Different Types of Estimate

2024-05-08 08:15:49
Share On Social Media :
Different types of estimate 
1.     Preliminary or approximate estimate or abstract estimate – is required for preliminary studies of various aspects of a work or project, to decide the financial position and policy for administrative sanction by the competent administrative authority. In case of commercial projects as irrigation projects, residential building project and similar projects which earn revenue income, the probable income may be worked out, and from the  preliminary estimate the approximate cost may be known and then it may be seen whether the investment, on the project is justified or not.
                             For non commercial projects or for projects giving no direct return, their necessary utility, availability of money etc, may be considered before final decision is taken.
            The approximate estimate is prepared from the practical knowledge and cost of similar works. This estimate is prepared showing separately the approximate cost of all important items of work as cost of land, cost of each building, cost of roads, water supply, sanitary works, etc.
2.     Plinth area estimate for building – prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specifications, heights and construction in the locality.
                     The plinth area should be calculated for the covered area by taking external dimension of the floor level. Courtyard and other open area should not be included in the plinth area. Plinth area estimate is only approximate and is a preliminary estimate, to know the approximate cost beforehand.
3.     Cube rate estimate for building - is a preliminary or an approximate estimate and prepared on the basis of the basis of cubical contents of the building, the cube rate being deducted from the cost of the similar building having similar specifications and construction in the locality.
                 Cube rate estimate is most accurate as compared to the plinth area estimate as the height of the building is also compared.
4.     Approximate quantity method - in this method, approximate total length of walls is found in running meter and this total length multiplied by the rate per running meter of wall gives a fairly accurate work. For this method, structure may be divided into two parts; i) foundation including plinth and ii) superstructure.
5.     Detailed or item rate estimate – is an accurate estimate and costs of working out the quantities of each item of works, and working the cost. Detailed estimate is prepared for technical sanction of the competent authority, for arranging, contract and for the execution of work.
     If in the abstracts of estimate form the columns of rates and amounts are left blank (to be filled by contractor) it is then known as bill of quantity. For detailed estimate, report, Specifications, drawing, design charts, rates, updated mode of measurement, standard circulars for taxes and insurances etc are required.
6.     Revised estimate – is a detailed estimate and is required to be prepared under any one of the following conditions.
a.     When the original sanctioned estimate is exceeded or likely to exceed by more than 5%.
b.     When the expenditure on a work exceeds or likely to exceed the amount of administrate sanctioned amount.
c.     When there are materials deviations from the original proposal, even though the cost may be met from sanctioned amount.
d.     When the expenditure on a work exceeds or likely to exceed the amount of administrative sanction by more than10%.
7.     Supplementary estimate – is a detailed estimate and is prepared when additional works required supplementing the original works, or when further development is regularly during the progress of work. This is a fresh detailed estimate of the additional works in addition to the original estimate.
8.     Supplementary and Revised estimate – when a work is partially abandoned and the estimated cost of the remaining work is less than 95% of the original work, i.e. less than 95% of the original sanctioned estimate or when there are material deviations and changes in the design which may cause substantial saving in the estimate, then the amount of the original estimate is revised by the competent authority. It is prepared and fresh technical sanction of the competent authority is obtained.
9.     Annual repair or Maintenance estimate – is detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.
10.  Extension and improvement estimate – when some changes and extension are required to be made in the old work, the cost of which cannot be met out of annual maintenance estimate, a detailed estimate of the additional work is prepared, called  the extension and improvement estimate.   

Leave a Comment

Author

Hello, I'm
Ramesh Singh

Gyan Provides online civil services preparation platform to crack the exam. Gyan Nepal online Lok Sewa preparation platform, for all civil examination notes, syllabus,question & answers other to crack the exam