Improving Nepal's Infrastructure Procurement: Bridging Lacunae in PPA/PPR, ADB MPC, and World Bank Rated Criteria
Ramesh singh
15 min read 182 views 0 comments
Share
Improving Nepal's Infrastructure Procurement:
Bridging Lacunae in PPA/PPR, ADB MPC, and World Bank Rated
Criteria
Author: Ramesh Kumar
Singh, Joint Secretary (DWRI)
Disclaimer:
The views expressed in this paper are personal and do not represent the
official position of the Department of Water Resources and Irrigation (DWRI).
List
of Abbreviations
- ADB: Asian Development Bank
- ALB: Abnormally Low Bid
- BBDMP: Bheri Babai Diversion Multipurpose Project
- CIAA: Commission for the Investigation of Abuse of
Authority
- DBO: Design-Build-Operate
- DWRI: Department of Water Resources and Irrigation
- EM: Electromechanical
- FIDIC: International Federation of Consulting Engineers
(Fédération Internationale des Ingénieurs-Conseils)
- GBR: Geotechnical Baseline Report
- HM: Hydromechanical
- IPC: Interim Payment Certificate
- JV: Joint Venture
- KPI: Key Performance Indicator
- LD: Liquidated Damages
- MDB: Multilateral Development Bank
- MIIP: Mahakali Irrigation Project
- MoF: Ministry of Finance
- MPC: Merit Point Criteria
- O&M: Operation and Maintenance
- OPEX: Operational Expenditure
- PPA: Public Procurement Act
- PPMO: Public Procurement Monitoring Office
- PPR: Public Procurement Rules
- PPSD: Project Procurement Strategy for Development
- SCADA: Supervisory Control and Data Acquisition
- SMDMP: Sunkoshi-Marin Diversion Multipurpose Project
- SPD: Standard Procurement Document
- SPP: Strategic Procurement Planning
- TBM: Tunnel Boring Machine
- WB: World Bank
Executive
Summary
Nepal's
cross-sectoral infrastructure procurement is governed by the Public Procurement
Act (PPA) 2063 and Public Procurement Rules (PPR) 2064, as amended by the PPA
Second Amendment (2083) and the PPR 16th Amendment (gazetted 2083/05/03).
This statutory framework is complemented by ADB's Merit Point Criteria (MPC)
and the World Bank's Rated Criteria, both of which became mandatory for
internationally advertised contracts in 2025–2026.
For
complex works exceeding NPR 1.5 billion, PPR Rule 26K(2) mandates a 50:50
technical-financial split. Within the 50-point technical envelope, the PPR
Rule 26K(3) table allocates 5 marks to Methodology, 75 marks to Past
Performance, 10 marks to Key Personnel, and 10 marks to Equipment (100-mark
evaluation sheet). The domestic lacuna is not that past performance is
undervalued—it is that Methodology, the criterion most relevant to Himalayan
tunnelling, DBO technology systems, and monsoon-constrained construction, is
mathematically marginalized at 5 marks (2.5 points of the final score).
The
MDB frameworks present complementary gaps: ADB MPC allows borrowers to define
past performance criteria but does not mandate that past performance be a
scored factor; the World Bank's Rated Criteria matrix does not include a
hazard-specific module for Himalayan geology or FIDIC ground-risk allocation.
Neither framework was designed with Nepal's seismic, monsoonal, and geological
profile in mind.
This
paper proposes a harmonized Three-Pillar MPC Model and a FIDIC Emerald
Book-aligned Geotechnical Baseline Report (GBR) requirement to bridge these
lacunae.
I.
The Statutory Baseline: PPR Rule 26K Analysis
Under
PPR Rule 26K(1), complex works exceeding NPR 1.5 billion require
a 50:50 technical-financial split (Rule 26K(2)). The Rule 26K(3) table
sets the following allocation:
When
evaluating the 50-point technical proposal, the PPR (Rule 26K(3))
expands this into a 100-mark evaluation sheet. The verified allocation is as
follows:
|
Group
#
|
Category
(PPR Rule 26K(3))
|
Marks
(Out of 100)
|
Equivalent
Weight (Out of 50)
|
|
1
|
Methodology
& Approach (कार्यसम्पादनको दृष्टिकोण)
|
5
|
2.5
points
|
|
2
|
Past
Performance (विगतको कार्यसम्पादन)
|
75
|
37.5
points
|
|
3
|
Key
Personnel (प्रस्तावित प्रमुख जनशक्ति)
|
10
|
5.0
points
|
|
4
|
Equipment
(उपकरणको उपलब्धता)
|
10
|
5.0
points
|
|
Total
|
100
|
50.0
points
|
Source:
PPR Rule 26K(3) table, as gazetted in the PPR 16th Amendment (2083/05/03). The
author has verified this allocation against the Nepali text.
The
Domestic Lacuna: The 75 marks for Past Performance ensure
that contractors with poor historical records are heavily penalized. However,
allocating only 5 marks to Methodology (2.5 points of the final
score) leaves evaluators structurally unable to differentiate technically
superior solutions (TBM selection, GBR response, SCADA reliability, monsoon
scheduling) from bare compliance. The 15–20 marks proposed in Section VIII
would require an offset from Past Performance (reducing it to 55–60 marks) or
from Equipment (reducing it to 5 marks), as detailed in the roadmap.
II.
Comparative Baseline: Bridging Multilateral Lacunae
|
Dimension
|
Nepal
PPA/PPR (Rule 26K)
|
ADB
Procurement Directive (2026) & MPC
|
World
Bank Rated Criteria (Feb 2025)
|
|
Legal
Status
|
Binding
statutory law.
|
Mandatory
for internationally advertised contracts since 1 Jan 2026.
|
Mandatory
for international competitive procurement where SPDs apply (excluding
pharmaceuticals/vaccines/commodities).
|
|
Technical-Financial
Split
|
Fixed
50:50 for PPMO-designated complex works > NPR 1.5B.
|
Minimum
50% for high/substantial risk + high value (>USD 10M).
|
Matrix:
High risk + High value = 50–80%; High risk + Low value = 60–100%;
Moderate/Low + High value = 10–40%; Moderate/Low + Low value = 20–30%.
|
|
Past
Performance
|
Scored
at 75 of 100 marks.
|
Borrower
defines criteria; not mandated as a scored factor. Risk of reduction to
pass/fail.
|
"Track
Record and Past Performance" is a recognized Rated Criteria category.
|
|
Abnormally
Low Bids (ALB)
|
Bids
>30% below estimate removed from evaluation (PPA 25(7B)).
|
Silent
within MPC text.
|
Addressed
ex-ante via clarification protocols.
|
|
Technical
Sub-criteria
|
Prescribed
bands (Methodology 5, Past Perf 75, Personnel 10, Equipment 10).
|
Borrower
defines, during SPP; ADB lists illustrative areas.
|
Borrower
defines during PPSD; weightings subject to Bank prior review.
|
The
MDB Lacuna:
- ADB MPC
does not mandate scored past performance, creating a risk that it is
reduced to a pass/fail gate.
- World Bank Rated Criteria
does not include a hazard-specific module for Himalayan geology, FIDIC GBR
integration, or monsoon construction windows. This is not a geographic
criticism; it reflects the absence of a hazard-risk module that any
borrower facing comparable geophysical risks could activate.
III.
Cross-Sectoral Evidentiary Cases
Water
& Irrigation (MIIP & BBDMP): MIIP is ADB-financed (US$125 million,
~500 tube wells, DBO prepaid smart-card system) and falls under PPA 67(b),
meaning ADB guidelines govern. BBDMP's 12.2 km TBM tunnel passes through
Siwalik rock, including the Babai and Bheri thrust faults . If BBDMP were
tendered today under Rule 26K, its fault-zone methodology would score at most 5
marks. The FIDIC Emerald Book (2019) provides the GBR mechanism for ground-risk
allocation, but this is not reflected in the PPR table.
SMDMP
(Sunkoshi-Marin): The Patel-Raman JV contract for the dam,
powerhouse, and hydromechanical works was terminated on 11 November 2025 after
11% physical progress against 60% of the contract period elapsed. The Public
Procurement Monitoring Office blacklisted the JV for three years. The bid was
approximately 32% below the engineer's estimate—a figure that would have
triggered automatic removal under the new 30% floor. This case is the strongest
evidence for the ALB lacuna, and it demonstrates why the 30% floor and the
75-mark Past Performance weighting are complementary, not contradictory: the
weighting penalizes historical non-performance; the floor prevents new low-ball
entry.
Transport,
Energy, Urban: The same 5-mark Methodology constraint
applies to hill-road bio-engineering, hydropower silt-erosion-resistant
runners, and urban drainage hydraulic modelling. These are illustrative of the
structural imbalance, not independent evidentiary claims.
IV.
The 21 Systemic Lacunae and Corrective Measures
A.
Legal and Institutional
- No legal harmonization protocol:
PPA 67(b) permits donor-guideline procurement, but there is no standing
legal annex that maps MDB scoring rules to PPA/PPR compliance. Impact:
This creates severe friction during NVC audits/CIAA investigation and
leaves Project Directors legally exposed when they follow ADB/World Bank
guidelines instead of strict domestic rules.
- Correction: Issue a Joint MoF/PPMO Legal Annex that maps ADB/World Bank
criteria to PPA/PPR thresholds, providing legal indemnity for good-faith
evaluators.
- Average-bid formula and judicial
intervention: The PPA Second Amendment introduced
the average-bid method. However, the Supreme Court (Writ No. 083-WO-0439)
has currently stayed the Ministry's circular (dated 2083/06/23)
implementing Rule 31Jha(1). Impact: While Rule 31Jha(2) provides a
mechanism to negotiate with the lowest bidder if all bids exceed the
estimate, the judicial stay creates procedural uncertainty.
- Correction: Once the court ruling finalizes, retain the statutory 30%
low-bid removal floor and formalize the Rule 31Jha high-bid negotiation,
while replacing mathematical averaging for price with an Ex-Ante ALB
Screening mechanism.
- Rule 26K sub-criteria imbalance:
As verified by the PPR table, Methodology is allocated only 5 marks (2.5
points) while Past Performance gets 75 marks. Impact: For complex
works like Himalayan tunnelling or DBO systems, this mathematically
prevents evaluators from rewarding technical innovation.
- Correction: Reallocate Methodology to 15–20 marks, offsetting the
difference from Past Performance (75→55–60) or Equipment (10→5).
- Regulatory instability:
Frequent PPR amendments (including the recent 16th Amendment) introduce
shifting rules mid-cycle. Impact: This causes uncertainty for
bidders and administrative disputes.
- Correction: Establish a mandatory Procurement Rules Stabilization
Period, fixing the applicable PPR version to the tender publication date.
B.
Evaluation Methodology
- ADB pass/fail risk:
ADB MPC allows the borrower to define past performance criteria, but does
not mandate that it be a scored factor. Impact: This creates a high
risk that past performance is reduced to a simple pass/fail gate, allowing
unperforming contractors with polished methodology papers to win.
- Correction: Supplement ADB MPC with scored past performance as a Pillar
2 criterion where the borrower has discretion.
- Lack of sector-specificity:
The statutory PPR table has no tailored modules for tunnelling, DBO,
Hydromechanical/Electromechanical (HM/EM) works, or monsoon constraints. Impact:
Evaluators are forced to use generic civil works templates for highly
specialized engineering.
- Correction: Issue PPMO technical guidance notes interpreting
"methodology" scoring to include geological behaviour-type
response, DBO system reliability, and seasonal planning.
- JV "credential renting":
In the terminated SMDMP contract, the lead partner held 65% of the JV. Impact:
Local firms often "rent" foreign credentials to secure technical
points without actual technical oversight, while passive partners simply
supply balance sheets.
- Correction: Align MPC/JV rules with statutory joint liability: The Lead
Partner must contribute at least 65% of past-performance points, and
passive partners are discounted. (Note: The 65% figure is an ownership
share, not a points rule; the corrective measure applies to points, not
ownership).
- No ex-ante ALB screening in ADB MPC:
ADB MPC text is silent on Abnormally Low Bids. Impact: Bids priced
dangerously below estimates pass directly into scoring, risking
mid-project abandonment.
- Correction: Establish Ex-Ante ALB Screening as a qualification-stage
criterion before MPC scoring begins.
C.
Capacity and Oversight
- Lack of panel expertise:
Generalist evaluation committees are often tasked with evaluating complex
tunnelling, SCADA, or HM/EM systems. Impact: This leads to poor
technical evaluations and defenseless decisions.
- Correction: Mandate an Independent Technical Expert (with voting rights)
for complex packages, funded by the ADB/World Bank.
- Evaluator hesitation ("Fear
Factor"): Evaluators frequently default to
pass/fail or lowest-price scoring out of fear of post-procurement CIAA
investigations. Impact: This undermines the entire purpose of
technical scoring.
- Correction: PPMO should issue standardized scoring templates and provide
legal indemnity to protect good-faith evaluators.
- Non-standardized documentation:
Technical scoring decisions often lack a clear evidentiary trail. Impact:
This makes the evaluation vulnerable to appeals and legal challenges from
rejected bidders.
- Correction: Mandate standardized MPC Scoring Sheets that require
page-referenced evidence for every point awarded.
- Lack of pre-bid training:
Domestic contractors are often unfamiliar with complex MPC requirements. Impact:
They submit non-responsive proposals, restricting market competition.
- Correction: Mandate Pre-Bid MPC Clarification Workshops for all complex
technical packages.
D.
Technical and Contract Management
- Absence of HM/EM modules:
Gates, turbines, and pumps are evaluated under generic civil works
templates. Impact: Critical factors like component life, metal
tolerances, and control systems are ignored.
- Correction: Develop targeted HM/EM modules focusing on design life,
marine-grade corrosion protection, and control reliability.
- Neglect of life-cycle OPEX:
Evaluation heavily weights initial Capital Expenditure (CAPEX), ignoring
long-term maintenance. Impact: This leads to higher long-term
operational costs (e.g., pumping inefficiencies).
- Correction: Embed quantifiable O&M Key Performance Indicators (KPIs)
(e.g., kWh/m³, downtime hours) directly into the financial formulas.
- Generic sustainability metrics:
Sustainability points are often granted for broad claims rather than
context-specific needs. Impact: This fails to address real
environmental impacts.
- Correction: Deploy a context-specific sustainability matrix tied
directly to environmental clearance commitments (e.g., bio-engineering,
groundwater recharge).
- Variation order exploitation:
Low bidders frequently use scope modifications (variation orders) to
recoup profit margins during execution. Impact: This undermines the
original competitive price.
- Correction: Institute mandatory Value Engineering Reviews for any
variation exceeding a defined threshold.
- Non-enforceable commitments:
Technical commitments made in successful bids are rarely transferred into
binding contract clauses. Impact: Bidders promise advanced
methodologies but deliver the bare minimum once the contract is signed.
- Correction: Annex the winning bidder's technical submission as a binding
Contract Schedule, with penalties and Interim Payment Certificate (IPC)
withholding linked to KPIs.
- Absence of SPP integration:
Procurement methods are chosen late in the project design phase without
market capacity assessments. Impact: This results in unrealistic
evaluation criteria and failed tenders.
- Correction: Mandate Strategic Procurement Planning (SPP) for all complex
packages before bid documents are finalized.
- Missing geotechnical scoring:
Himalayan geological uncertainties are treated with general civil
templates. Impact: Contractors do not adequately prepare for fault
zones, squeezing ground, or water ingress.
- Correction: Require Geotechnical Risk Mitigation Scoring for all deep
excavation, slope stabilization, and tunnelling packages.
- No monsoon scoring:
Monsoon and seasonal constraints are completely absent from the evaluation
criteria. Impact: This ignores Nepal's climatic reality, leading to
inevitable delays and cost overruns.
- Correction: Require Seasonal Construction Plan scoring: dry-season
critical path, monsoon drainage/slope protection, and material stockpile
plans.
- No FIDIC risk-allocation scoring:
FIDIC risk allocation logic (particularly the Emerald Book's GBR) is not
integrated into bid scoring. Impact: There is a disconnect between
what is scored and what is managed during the contract.
- Correction: Require a FIDIC Risk Allocation Response Matrix for the
selected contract condition.
V.
The Three-Pillar Harmonized MPC Model
The
model operates within Nepal's statutory framework. For MDB-financed packages
(PPA 67(b)), it can be applied fully.
Total
Technical Score (
) = 
Mapping
to Rule 26K(3):
- Pillar 1 (Project-Specific Technical
Requirements) maps to Group 1 (Methodology) and
Group 4 (Equipment).
- Pillar 2 (Past Performance Track
Record) maps to Group 2 (Past Performance).
- Pillar 3 (Activity-Specific Relevant
Experience) maps to Group 3 (Key Personnel).
Pillar
1 (Methodology & Equipment): Geological behaviour-type response, DBO
system reliability, monsoon scheduling, equipment suitability. FIDIC GBR
alignment for tunnelling.
Pillar
2 (Past Performance):
. JV Rule: Lead
Partner contributes ≥65% of points. Barrier-to-entry safeguard: new firms may
substitute key-personnel experience, subject to verification (independent
expert sign-off) and a cap (e.g., 50% of the firm-level past-performance
requirement).
Pillar
3 (Key Personnel): Verified field experience in comparable
geology and climate; activity-specific quantities.
VI.
Contractual Integration: From Scoring to Delivery
The
winning bidder's technical submission (including scored commitments) is annexed
as a binding Contract Schedule. Remedies: LDs for O&M/efficiency
failures; penalties for key-personnel substitution; IPC withholding for
equipment non-mobilization. For tunnelling, the Emerald Book GBR converts
geological-response commitments into measurable baseline obligations.
VII.
Interface with Nepal's 2026 Procurement Reform
- PPA Second Amendment (2083): Introduced
average-bid method; PPA 25(7B) removes bids >30% below estimate.
- PPR 16th Amendment (gazetted
2083/05/03): Raised Rule 26K(1) threshold to NPR
1.5B; Rule 26K(3) table as analysed above.
- JV Liability: Strengthened joint
liability.
Critical
Judgment: The reforms in the PPA Second Amendment
address price reasonableness, not technical capability. Rule 31Jha governs the
high-bid negotiation process, while PPA 25(7B) removes low bids (>30% below
estimate). The current Supreme Court stay is focused on the procedural
implementation of this averaging rule. Therefore, price screening (Rule 31Jha
& the 30% floor) and capability identification (the Three-Pillar MPC) are
complementary, not substitutes. Nepal should reform its technical sub-criteria
while allowing the Court to finalize the price-averaging mechanics.
VIII.
Actionable Implementation Roadmap
|
#
|
Action
|
Responsible
Party
|
Legal
Instrument
|
|
1
|
Nepal-Specific
MPC Legal Annex under PPA 67(b), with legal indemnity.
|
MoF
+ PPMO + ADB/WB
|
Joint
Directive
|
|
2
|
Amend
PPR Rule 26K(3): Methodology 5→15–20 marks; offset from
Past Performance (75→55–60) or Equipment (10→5).
|
PPMO
|
PPR
Amendment
|
|
3
|
PPMO
Technical Guidance Notes for tunnelling, DBO, HM/EM, monsoon
scheduling.
|
PPMO
+ DWRI + experts
|
PPMO
Guidance Note
|
|
4
|
Independent
Technical Expert with voting rights on complex
evaluations.
|
PPMO
+ ADB/WB
|
PPR
Amendment
|
|
5
|
Post-Evaluation
Review with Legal Indemnity.
|
PPMO
|
PPMO
Directive
|
|
6
|
FIDIC
Risk Allocation Response Matrix and Seasonal Construction Plan.
|
Executing
agencies
|
Standard
Bidding Document
|
|
7
|
Binding
Contract Schedule with KPI-linked IPCs.
|
Executing
agencies + MDBs
|
Contract
Provisions
|
|
8
|
Ex-Ante
ALB Screening (retaining the 30% floor).
|
PPMO
+ ADB
|
PPR
Amendment
|
IX.
Conclusion
Nepal's
PPA/PPR provides a legally binding foundation that prioritises contractor
reliability. The lacuna is not that past performance is undervalued—it is that Methodology
is mathematically marginalised at 5 marks, and that ADB MPC and World Bank
Rated Criteria lack hazard-specific modules for Himalayan geology and FIDIC
ground-risk integration. By recalibrating Rule 26K(3), introducing
sector-specific guidance, and integrating the FIDIC Emerald Book GBR, Nepal can
align its procurement with international best practice while retaining its
statutory commitment to contractor accountability.
References
- Public Procurement Act, 2063 (Second
Amendment, 2083).
- Public Procurement Rules, 2064 (16th
Amendment, gazetted 2083/05/03).
- Supreme Court of Nepal, Writ No.
083-WO-0439 (Interim Order on Rule 31Jha implementation circular,
2083/07/10)
- World Bank, Procurement Regulations
for IPF Borrowers, Sixth Edition (February 2025) .
- World Bank, Rated Criteria Overview
.
- ADB, Procurement Directive (2026)
and Merit Point Criteria .
- FIDIC Emerald Book (2019) –
Conditions of Contract for Underground Works.
- The Kathmandu Post, "Sunkoshi
Marin contract cancellation defers Madhesh irrigation dream" (1 Nov
2026) .
- The Kathmandu Post, "Contractor
blacklisted for delays in Sunkoshi-Marin diversion project" (27 May
2026) .
- IOPscience, "Study on the
construction mechanical response of the double-shield TBMs of a long
diversion tunnel crossing a fault fracture zone" (BBDMP) .
- Onesphere Law Associates,
"Public Procurement Act in Nepal: A Bidder Guide 2026" (PPA
25(7B) 30% floor)