Improving Nepal's Infrastructure Procurement: Bridging Lacunae in PPA/PPR, ADB MPC, and World Bank Rated Criteria
Public Administration

Improving Nepal's Infrastructure Procurement: Bridging Lacunae in PPA/PPR, ADB MPC, and World Bank Rated Criteria

Ramesh singh

15 min read 182 views 0 comments

Share
Improving Nepal's Infrastructure Procurement: Bridging Lacunae in PPA/PPR, ADB MPC, and World Bank Rated Criteria
 
Author: Ramesh Kumar Singh, Joint Secretary (DWRI)
Disclaimer: The views expressed in this paper are personal and do not represent the official position of the Department of Water Resources and Irrigation (DWRI).
 
List of Abbreviations
  • ADB: Asian Development Bank
 
  • ALB: Abnormally Low Bid
 
  • BBDMP: Bheri Babai Diversion Multipurpose Project
 
  • CIAA: Commission for the Investigation of Abuse of Authority
 
  • DBO: Design-Build-Operate
 
  • DWRI: Department of Water Resources and Irrigation
 
  • EM: Electromechanical
 
  • FIDIC: International Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conseils)
 
  • GBR: Geotechnical Baseline Report
 
  • HM: Hydromechanical
 
  • IPC: Interim Payment Certificate
 
  • JV: Joint Venture
 
  • KPI: Key Performance Indicator
 
  • LD: Liquidated Damages
 
  • MDB: Multilateral Development Bank
 
  • MIIP: Mahakali Irrigation Project
 
  • MoF: Ministry of Finance
 
  • MPC: Merit Point Criteria
 
  • O&M: Operation and Maintenance
 
  • OPEX: Operational Expenditure
 
  • PPA: Public Procurement Act
 
  • PPMO: Public Procurement Monitoring Office
 
  • PPR: Public Procurement Rules
 
  • PPSD: Project Procurement Strategy for Development
 
  • SCADA: Supervisory Control and Data Acquisition
 
  • SMDMP: Sunkoshi-Marin Diversion Multipurpose Project
 
  • SPD: Standard Procurement Document
 
  • SPP: Strategic Procurement Planning
 
  • TBM: Tunnel Boring Machine
 
  • WB: World Bank
 
Executive Summary
Nepal's cross-sectoral infrastructure procurement is governed by the Public Procurement Act (PPA) 2063 and Public Procurement Rules (PPR) 2064, as amended by the PPA Second Amendment (2083) and the PPR 16th Amendment (gazetted 2083/05/03). This statutory framework is complemented by ADB's Merit Point Criteria (MPC) and the World Bank's Rated Criteria, both of which became mandatory for internationally advertised contracts in 2025–2026.
For complex works exceeding NPR 1.5 billion, PPR Rule 26K(2) mandates a 50:50 technical-financial split. Within the 50-point technical envelope, the PPR Rule 26K(3) table allocates 5 marks to Methodology, 75 marks to Past Performance, 10 marks to Key Personnel, and 10 marks to Equipment (100-mark evaluation sheet). The domestic lacuna is not that past performance is undervalued—it is that Methodology, the criterion most relevant to Himalayan tunnelling, DBO technology systems, and monsoon-constrained construction, is mathematically marginalized at 5 marks (2.5 points of the final score).
The MDB frameworks present complementary gaps: ADB MPC allows borrowers to define past performance criteria but does not mandate that past performance be a scored factor; the World Bank's Rated Criteria matrix does not include a hazard-specific module for Himalayan geology or FIDIC ground-risk allocation. Neither framework was designed with Nepal's seismic, monsoonal, and geological profile in mind.
This paper proposes a harmonized Three-Pillar MPC Model and a FIDIC Emerald Book-aligned Geotechnical Baseline Report (GBR) requirement to bridge these lacunae.
I. The Statutory Baseline: PPR Rule 26K Analysis
Under PPR Rule 26K(1), complex works exceeding NPR 1.5 billion require a 50:50 technical-financial split (Rule 26K(2)). The Rule 26K(3) table sets the following allocation:
 
When evaluating the 50-point technical proposal, the PPR (Rule 26K(3)) expands this into a 100-mark evaluation sheet. The verified allocation is as follows:
Group #
Category (PPR Rule 26K(3))
Marks (Out of 100)
Equivalent Weight (Out of 50)
1
Methodology & Approach (कार्यसम्पादनको दृष्टिकोण)
5
2.5 points
2
Past Performance (विगतको कार्यसम्पादन)
75
37.5 points
3
Key Personnel (प्रस्तावित प्रमुख जनशक्ति)
10
5.0 points
4
Equipment (उपकरणको उपलब्धता)
10
5.0 points
Total
100
50.0 points
 
Source: PPR Rule 26K(3) table, as gazetted in the PPR 16th Amendment (2083/05/03). The author has verified this allocation against the Nepali text.
The Domestic Lacuna: The 75 marks for Past Performance ensure that contractors with poor historical records are heavily penalized. However, allocating only 5 marks to Methodology (2.5 points of the final score) leaves evaluators structurally unable to differentiate technically superior solutions (TBM selection, GBR response, SCADA reliability, monsoon scheduling) from bare compliance. The 15–20 marks proposed in Section VIII would require an offset from Past Performance (reducing it to 55–60 marks) or from Equipment (reducing it to 5 marks), as detailed in the roadmap.
II. Comparative Baseline: Bridging Multilateral Lacunae
Dimension
Nepal PPA/PPR (Rule 26K)
ADB Procurement Directive (2026) & MPC
World Bank Rated Criteria (Feb 2025)
Legal Status
Binding statutory law.
Mandatory for internationally advertised contracts since 1 Jan 2026.
Mandatory for international competitive procurement where SPDs apply (excluding pharmaceuticals/vaccines/commodities).
Technical-Financial Split
Fixed 50:50 for PPMO-designated complex works > NPR 1.5B.
Minimum 50% for high/substantial risk + high value (>USD 10M).
Matrix: High risk + High value = 50–80%; High risk + Low value = 60–100%; Moderate/Low + High value = 10–40%; Moderate/Low + Low value = 20–30%.
Past Performance
Scored at 75 of 100 marks.
Borrower defines criteria; not mandated as a scored factor. Risk of reduction to pass/fail.
"Track Record and Past Performance" is a recognized Rated Criteria category.
Abnormally Low Bids (ALB)
Bids >30% below estimate removed from evaluation (PPA 25(7B)).
Silent within MPC text.
Addressed ex-ante via clarification protocols.
Technical Sub-criteria
Prescribed bands (Methodology 5, Past Perf 75, Personnel 10, Equipment 10).
Borrower defines, during SPP; ADB lists illustrative areas.
Borrower defines during PPSD; weightings subject to Bank prior review.
The MDB Lacuna:
  • ADB MPC does not mandate scored past performance, creating a risk that it is reduced to a pass/fail gate.
  • World Bank Rated Criteria does not include a hazard-specific module for Himalayan geology, FIDIC GBR integration, or monsoon construction windows. This is not a geographic criticism; it reflects the absence of a hazard-risk module that any borrower facing comparable geophysical risks could activate.
III. Cross-Sectoral Evidentiary Cases
Water & Irrigation (MIIP & BBDMP): MIIP is ADB-financed (US$125 million, ~500 tube wells, DBO prepaid smart-card system) and falls under PPA 67(b), meaning ADB guidelines govern. BBDMP's 12.2 km TBM tunnel passes through Siwalik rock, including the Babai and Bheri thrust faults . If BBDMP were tendered today under Rule 26K, its fault-zone methodology would score at most 5 marks. The FIDIC Emerald Book (2019) provides the GBR mechanism for ground-risk allocation, but this is not reflected in the PPR table.
SMDMP (Sunkoshi-Marin): The Patel-Raman JV contract for the dam, powerhouse, and hydromechanical works was terminated on 11 November 2025 after 11% physical progress against 60% of the contract period elapsed. The Public Procurement Monitoring Office blacklisted the JV for three years. The bid was approximately 32% below the engineer's estimate—a figure that would have triggered automatic removal under the new 30% floor. This case is the strongest evidence for the ALB lacuna, and it demonstrates why the 30% floor and the 75-mark Past Performance weighting are complementary, not contradictory: the weighting penalizes historical non-performance; the floor prevents new low-ball entry.
Transport, Energy, Urban: The same 5-mark Methodology constraint applies to hill-road bio-engineering, hydropower silt-erosion-resistant runners, and urban drainage hydraulic modelling. These are illustrative of the structural imbalance, not independent evidentiary claims.
IV. The 21 Systemic Lacunae and Corrective Measures
A. Legal and Institutional
  1. No legal harmonization protocol: PPA 67(b) permits donor-guideline procurement, but there is no standing legal annex that maps MDB scoring rules to PPA/PPR compliance. Impact: This creates severe friction during NVC audits/CIAA investigation and leaves Project Directors legally exposed when they follow ADB/World Bank guidelines instead of strict domestic rules.
    • Correction: Issue a Joint MoF/PPMO Legal Annex that maps ADB/World Bank criteria to PPA/PPR thresholds, providing legal indemnity for good-faith evaluators.
  2. Average-bid formula and judicial intervention: The PPA Second Amendment introduced the average-bid method. However, the Supreme Court (Writ No. 083-WO-0439) has currently stayed the Ministry's circular (dated 2083/06/23) implementing Rule 31Jha(1). Impact: While Rule 31Jha(2) provides a mechanism to negotiate with the lowest bidder if all bids exceed the estimate, the judicial stay creates procedural uncertainty.
    • Correction: Once the court ruling finalizes, retain the statutory 30% low-bid removal floor and formalize the Rule 31Jha high-bid negotiation, while replacing mathematical averaging for price with an Ex-Ante ALB Screening mechanism.
  3. Rule 26K sub-criteria imbalance: As verified by the PPR table, Methodology is allocated only 5 marks (2.5 points) while Past Performance gets 75 marks. Impact: For complex works like Himalayan tunnelling or DBO systems, this mathematically prevents evaluators from rewarding technical innovation.
    • Correction: Reallocate Methodology to 15–20 marks, offsetting the difference from Past Performance (75→55–60) or Equipment (10→5).
  4. Regulatory instability: Frequent PPR amendments (including the recent 16th Amendment) introduce shifting rules mid-cycle. Impact: This causes uncertainty for bidders and administrative disputes.
    • Correction: Establish a mandatory Procurement Rules Stabilization Period, fixing the applicable PPR version to the tender publication date.
B. Evaluation Methodology
  1. ADB pass/fail risk: ADB MPC allows the borrower to define past performance criteria, but does not mandate that it be a scored factor. Impact: This creates a high risk that past performance is reduced to a simple pass/fail gate, allowing unperforming contractors with polished methodology papers to win.
    • Correction: Supplement ADB MPC with scored past performance as a Pillar 2 criterion where the borrower has discretion.
  2. Lack of sector-specificity: The statutory PPR table has no tailored modules for tunnelling, DBO, Hydromechanical/Electromechanical (HM/EM) works, or monsoon constraints. Impact: Evaluators are forced to use generic civil works templates for highly specialized engineering.
    • Correction: Issue PPMO technical guidance notes interpreting "methodology" scoring to include geological behaviour-type response, DBO system reliability, and seasonal planning.
  3. JV "credential renting": In the terminated SMDMP contract, the lead partner held 65% of the JV. Impact: Local firms often "rent" foreign credentials to secure technical points without actual technical oversight, while passive partners simply supply balance sheets.
    • Correction: Align MPC/JV rules with statutory joint liability: The Lead Partner must contribute at least 65% of past-performance points, and passive partners are discounted. (Note: The 65% figure is an ownership share, not a points rule; the corrective measure applies to points, not ownership).
  4. No ex-ante ALB screening in ADB MPC: ADB MPC text is silent on Abnormally Low Bids. Impact: Bids priced dangerously below estimates pass directly into scoring, risking mid-project abandonment.
    • Correction: Establish Ex-Ante ALB Screening as a qualification-stage criterion before MPC scoring begins.
C. Capacity and Oversight
  1. Lack of panel expertise: Generalist evaluation committees are often tasked with evaluating complex tunnelling, SCADA, or HM/EM systems. Impact: This leads to poor technical evaluations and defenseless decisions.
    • Correction: Mandate an Independent Technical Expert (with voting rights) for complex packages, funded by the ADB/World Bank.
  2. Evaluator hesitation ("Fear Factor"): Evaluators frequently default to pass/fail or lowest-price scoring out of fear of post-procurement CIAA investigations. Impact: This undermines the entire purpose of technical scoring.
    • Correction: PPMO should issue standardized scoring templates and provide legal indemnity to protect good-faith evaluators.
  3. Non-standardized documentation: Technical scoring decisions often lack a clear evidentiary trail. Impact: This makes the evaluation vulnerable to appeals and legal challenges from rejected bidders.
    • Correction: Mandate standardized MPC Scoring Sheets that require page-referenced evidence for every point awarded.
  4. Lack of pre-bid training: Domestic contractors are often unfamiliar with complex MPC requirements. Impact: They submit non-responsive proposals, restricting market competition.
    • Correction: Mandate Pre-Bid MPC Clarification Workshops for all complex technical packages.
D. Technical and Contract Management
  1. Absence of HM/EM modules: Gates, turbines, and pumps are evaluated under generic civil works templates. Impact: Critical factors like component life, metal tolerances, and control systems are ignored.
    • Correction: Develop targeted HM/EM modules focusing on design life, marine-grade corrosion protection, and control reliability.
  2. Neglect of life-cycle OPEX: Evaluation heavily weights initial Capital Expenditure (CAPEX), ignoring long-term maintenance. Impact: This leads to higher long-term operational costs (e.g., pumping inefficiencies).
    • Correction: Embed quantifiable O&M Key Performance Indicators (KPIs) (e.g., kWh/m³, downtime hours) directly into the financial formulas.
  3. Generic sustainability metrics: Sustainability points are often granted for broad claims rather than context-specific needs. Impact: This fails to address real environmental impacts.
    • Correction: Deploy a context-specific sustainability matrix tied directly to environmental clearance commitments (e.g., bio-engineering, groundwater recharge).
  4. Variation order exploitation: Low bidders frequently use scope modifications (variation orders) to recoup profit margins during execution. Impact: This undermines the original competitive price.
    • Correction: Institute mandatory Value Engineering Reviews for any variation exceeding a defined threshold.
  5. Non-enforceable commitments: Technical commitments made in successful bids are rarely transferred into binding contract clauses. Impact: Bidders promise advanced methodologies but deliver the bare minimum once the contract is signed.
    • Correction: Annex the winning bidder's technical submission as a binding Contract Schedule, with penalties and Interim Payment Certificate (IPC) withholding linked to KPIs.
  6. Absence of SPP integration: Procurement methods are chosen late in the project design phase without market capacity assessments. Impact: This results in unrealistic evaluation criteria and failed tenders.
    • Correction: Mandate Strategic Procurement Planning (SPP) for all complex packages before bid documents are finalized.
  7. Missing geotechnical scoring: Himalayan geological uncertainties are treated with general civil templates. Impact: Contractors do not adequately prepare for fault zones, squeezing ground, or water ingress.
    • Correction: Require Geotechnical Risk Mitigation Scoring for all deep excavation, slope stabilization, and tunnelling packages.
  8. No monsoon scoring: Monsoon and seasonal constraints are completely absent from the evaluation criteria. Impact: This ignores Nepal's climatic reality, leading to inevitable delays and cost overruns.
    • Correction: Require Seasonal Construction Plan scoring: dry-season critical path, monsoon drainage/slope protection, and material stockpile plans.
  9. No FIDIC risk-allocation scoring: FIDIC risk allocation logic (particularly the Emerald Book's GBR) is not integrated into bid scoring. Impact: There is a disconnect between what is scored and what is managed during the contract.
    • Correction: Require a FIDIC Risk Allocation Response Matrix for the selected contract condition.
V. The Three-Pillar Harmonized MPC Model
The model operates within Nepal's statutory framework. For MDB-financed packages (PPA 67(b)), it can be applied fully.
Total Technical Score () =
Mapping to Rule 26K(3):
  • Pillar 1 (Project-Specific Technical Requirements) maps to Group 1 (Methodology) and Group 4 (Equipment).
  • Pillar 2 (Past Performance Track Record) maps to Group 2 (Past Performance).
  • Pillar 3 (Activity-Specific Relevant Experience) maps to Group 3 (Key Personnel).
Pillar 1 (Methodology & Equipment): Geological behaviour-type response, DBO system reliability, monsoon scheduling, equipment suitability. FIDIC GBR alignment for tunnelling.
Pillar 2 (Past Performance): . JV Rule: Lead Partner contributes ≥65% of points. Barrier-to-entry safeguard: new firms may substitute key-personnel experience, subject to verification (independent expert sign-off) and a cap (e.g., 50% of the firm-level past-performance requirement).
Pillar 3 (Key Personnel): Verified field experience in comparable geology and climate; activity-specific quantities.
VI. Contractual Integration: From Scoring to Delivery
The winning bidder's technical submission (including scored commitments) is annexed as a binding Contract Schedule. Remedies: LDs for O&M/efficiency failures; penalties for key-personnel substitution; IPC withholding for equipment non-mobilization. For tunnelling, the Emerald Book GBR converts geological-response commitments into measurable baseline obligations.
VII. Interface with Nepal's 2026 Procurement Reform
  • PPA Second Amendment (2083): Introduced average-bid method; PPA 25(7B) removes bids >30% below estimate.
  • PPR 16th Amendment (gazetted 2083/05/03): Raised Rule 26K(1) threshold to NPR 1.5B; Rule 26K(3) table as analysed above.
  • JV Liability: Strengthened joint liability.
Critical Judgment: The reforms in the PPA Second Amendment address price reasonableness, not technical capability. Rule 31Jha governs the high-bid negotiation process, while PPA 25(7B) removes low bids (>30% below estimate). The current Supreme Court stay is focused on the procedural implementation of this averaging rule. Therefore, price screening (Rule 31Jha & the 30% floor) and capability identification (the Three-Pillar MPC) are complementary, not substitutes. Nepal should reform its technical sub-criteria while allowing the Court to finalize the price-averaging mechanics.
VIII. Actionable Implementation Roadmap
#
Action
Responsible Party
Legal Instrument
1
Nepal-Specific MPC Legal Annex under PPA 67(b), with legal indemnity.
MoF + PPMO + ADB/WB
Joint Directive
2
Amend PPR Rule 26K(3): Methodology 5→15–20 marks; offset from Past Performance (75→55–60) or Equipment (10→5).
PPMO
PPR Amendment
3
PPMO Technical Guidance Notes for tunnelling, DBO, HM/EM, monsoon scheduling.
PPMO + DWRI + experts
PPMO Guidance Note
4
Independent Technical Expert with voting rights on complex evaluations.
PPMO + ADB/WB
PPR Amendment
5
Post-Evaluation Review with Legal Indemnity.
PPMO
PPMO Directive
6
FIDIC Risk Allocation Response Matrix and Seasonal Construction Plan.
Executing agencies
Standard Bidding Document
7
Binding Contract Schedule with KPI-linked IPCs.
Executing agencies + MDBs
Contract Provisions
8
Ex-Ante ALB Screening (retaining the 30% floor).
PPMO + ADB
PPR Amendment
 
IX. Conclusion
Nepal's PPA/PPR provides a legally binding foundation that prioritises contractor reliability. The lacuna is not that past performance is undervalued—it is that Methodology is mathematically marginalised at 5 marks, and that ADB MPC and World Bank Rated Criteria lack hazard-specific modules for Himalayan geology and FIDIC ground-risk integration. By recalibrating Rule 26K(3), introducing sector-specific guidance, and integrating the FIDIC Emerald Book GBR, Nepal can align its procurement with international best practice while retaining its statutory commitment to contractor accountability.
References
  1. Public Procurement Act, 2063 (Second Amendment, 2083).
  2. Public Procurement Rules, 2064 (16th Amendment, gazetted 2083/05/03).
  3. Supreme Court of Nepal, Writ No. 083-WO-0439 (Interim Order on Rule 31Jha implementation circular, 2083/07/10)
  4. World Bank, Procurement Regulations for IPF Borrowers, Sixth Edition (February 2025) .
  5. World Bank, Rated Criteria Overview .
  6. ADB, Procurement Directive (2026) and Merit Point Criteria .
  7. FIDIC Emerald Book (2019) – Conditions of Contract for Underground Works.
  8. The Kathmandu Post, "Sunkoshi Marin contract cancellation defers Madhesh irrigation dream" (1 Nov 2026) .
  9. The Kathmandu Post, "Contractor blacklisted for delays in Sunkoshi-Marin diversion project" (27 May 2026) .
  10. IOPscience, "Study on the construction mechanical response of the double-shield TBMs of a long diversion tunnel crossing a fault fracture zone" (BBDMP) .
  11. Onesphere Law Associates, "Public Procurement Act in Nepal: A Bidder Guide 2026" (PPA 25(7B) 30% floor)